475 questions in the Paytm pattern. Try 5 real questions below; tap an option to check.

Question 1 · Medium
Arun can do a piece of work in 40 days, but Bala can do the same work in 5 days less, than Arun, when working alone. Arun and Bala both started the work together but Bala left after some days and Arun finished the remaining work in 30 days with half of his efficiency but he did the work with Bala with his complete efficiency. For how many days they had worked together?
Correct answer: A. Full solutions and timing analysis come with the test.
Question 2 · Hard
Kiran can do a work in 20 days, while Karan can do the same work in 25 days. They started the work jointly. Few days later Suman also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs.1000. What is the share of Suman?
Correct answer: A. Full solutions and timing analysis come with the test.
Question 3 · Hard
7 Indian and 4 American finish a job in 6 days. 7 African and 3 American finish the same job in 8 days. The efficiency of each person of a particular nationality is same but different from others. One Indian One American and One African will complete the work in:
Correct answer: A. Full solutions and timing analysis come with the test.
Question 4 · Hard
Chitra is twice efficient as Arun. Bala takes thrice as many days as Chitra. Arun takes 12 days to finish the work alone. If they work in pairs(i.e Arun-Bala, Bala-Chitra, Chitra-Arun) starting with Arun – Bala on the first day, Bala – Chitra on the second day and Chitra – Arun on the third day and so on, then how many days are required to finish the work?
Correct answer: A. Full solutions and timing analysis come with the test.
Question 5 · Hard
A work is done by 30 workers not all of them have the same capacity to work. Every day exactly 2 workers, do the work with no pair of workers working together twice. Even after all possible pairs have worked once, all the workers together works for six more days to finish the work. Find the number of days in which all the workers together will finish the work?
Correct answer: A. Full solutions and timing analysis come with the test.
Questions, answered
Short, honest answers. Ask a counsellor if yours isn’t here.
Talk to a certified counsellor on WhatsApp.
Ask a counsellorAre these real exam questions?
Is it free?
Do I get a rank?
Practice is free. Planning is personal.
Turn mock scores into a study plan and an exam strategy with a counsellor.

Explore more
More in Youth4Work student sections

Youth4Work student sections
Deloitte placement papers with answers
Open
Youth4Work student sections
Mu Sigma placement papers with answers
Open
Youth4Work student sections
Free mock tests
Open
Youth4Work student sections
IBPS PO Prelim Exam mock tests (free)
Open
Youth4Work student sections
JEE Main mock tests (free)
Open
Youth4Work student sections
NEET mock tests (free)
Open
Youth4Work student sections
Placement papers for 78 companies
Open
Youth4Work student sections